PROJECT LOCATION | Dolakha District |
PROFESSIONAL STAFF | 4 |
OTHER STAFF | 3 |
NAME OF CLIENT/DONOR | Royal Danish Embassy |
NO. OF PROFESSIONAL MAN MONTHS | 52 |
NO. OF OTHER MAN MONTHS | 39 |
START DATE (Month/Year) | June 1997 |
COMPLETION DATE (Month/Year) | September 1998 |
APPROX. VALUE OF SERVICES | NRs. 600,000 |
NAME OF ASSOCIATION FIRM, IF ANY: | |
NO. OF MAN-MONTHS OF PROFESSIONAL STAFF PROVIDED BY ASSOCIATED FIRM: | Not Applicable |
NAME OF SENIOR STAFF
Mr. Thaneswor Prasad Pokhrel, Mr. Gopal Shivakoti, Mr. Subhasha Nanda Vaidya and Mr. Ram Prasad Uprety were responsible for the implementation, supervision and monitoring of the project activities. |
NARRATIVE DESCRIPTION OF PROJECT
The major objective of the Program, initiated as part of the Income Generating Project for Women Farmers along Arniko Highway, was to involve 100 - 500 farm families and raise their annual income by at least Rs. 6,000. |
DESCRIPTION OF SERVICES PROVIDED
|